Verna



Verna-single-page

State of the art technology in structural engineering, innovative architecture, most modern amenities and a picturesque location, this is what Verna brings to you. It is a much sought-after residential address listing it as one of the most expensive and upmarket housing locality.

Location : Nalanchira, Trivandrum
Type of Units : 2BHK, 2BHK+ Study, 3BHK, 3BHK + Study & 4BHK
Building permit No : UE1/BA/150/2013
Airport authority of india NOC ID : THIR/SOUTH/B/072313/15335

Online booking form
Common amenities
  • CCTV
  • Bio-metric Entry for entrance lobby
  • Fitness centre
  • Wi-Fi
  • Video Door phone
  • Stretcher Lift
  • Roof top party area
  • Cable TV
  • Kid’s play area
  • Guest Suite
  • Association room
Resource Conservation
  • Rain water harvesting
  • Solar Energy for Yard & Common area Lighting

Nearby convenience Within 3 Kms radius

Schools Christ Nagar, ISC Holy Angels, Nirmala Bhavan, St. Shanthal, Salvation Army, Chinmaya Vidhyalaya, St. Thomas.
Colleges MG College, , Mar Ivanious, Mar Basellious,  Law Academy.
Hospitals KJK Hospital, Swanthwana,SUT, Cosmopolitan, Medical College, RCC.
Departmental Stores and Shoping Centres Big Bazaar, Kedaram Shoiping Centre, Spencer’s Margin Free, More For You, Azad Bread Factory, Nilgiris, Reliance Fresh Max.
Entertainment Museum & Zoo, Tennis Club, Nishagandhi, Kalabhavan Theratre.
Hotels & Restaurant Taj Vivantha, Windstor rajadhani, Sindoor Palace, Kalavara, Muscot.
Progress as of July , 2017

Block work – 100% work completed, Internal Plastering – 96% work completed, External plastering – 100% work completed, Internal Plumbing – 85% work completed, Electrical Internal wall chasing & Box fitting – 98% completed, wire pulling – 57% completed, Ramp work – 40% completed, Tiling work – 70% completed, Internal Putty work – 96% completed, Balcony handrail fixing:-100% completed. First coat External Putty Work-100% Completed. Staircase – handrail fixing – 82% Completed. ​

Progress as of June , 2017

Block work – 100% work completed, Internal Plastering – 95% work completed, External plastering – 100% work completed, Internal Plumbing – 84% work completed, Electrical Internal wall chasing & Box fitting – 98% completed, wire pulling – 55% completed, Ramp work – 37% completed, Tiling work – 65% completed, Internal Putty work – 95% completed, Balcony handrail fixing:-100% completed. First coat External Putty Work-100% Completed. Staircase – handrail fixing – 80% Completed.​

Progress  as of May 2017

Block work – 100% work completed, Internal Plastering – 93% work completed, External plastering – 100% work completed, Internal Plumbing – 83% work completed, Electrical Internal wall chasing & Box fitting – 97% completed, wire pulling – 50% completed, Ramp work – 35% completed, Tiling work – 60% completed, Internal Putty work – 92% completed, Balcony handrail fixing:-100% completed. External Putty Work-52% Completed Staircase – handrail fixing – 75% Completed.

Progress as of April , 2017

Block work – 100% work completed, Internal Plastering –  92% work completed, External plastering –  100% work completed, Internal Plumbing – 80% work completed, Electrical Internal wall chasing & Box fitting – 95% completed, wire pulling – 50% completed, Ramp work – 30% completed, Tiling work – 55% completed, Internal Putty work – 90% completed, Balcony handrail fixing:-100% completed. External Putty Work-50% Completed Staircase –  handrail fixing – 50% Completed.

Progress as of March 2017

Block work:-100% work completed, Internal Plastering :- 92% work completed, External plastering :- 90% work completed, Internal Plumbing:-75% work completed, Electrical Internal wall chasing & Box fitting:-90% completed, wire pulling :-50% completed, Ramp work :-30% completed, Tiling work :-50% completed, Internal Putty work :-85% completed, Balcony handrail fixing:-80% completed. External Putty Work-30% Completed

Progress as of February 2017

Block work:-100% work completed, Internal Plastering :- 90% work completed, External plastering :- 80% work completed, Internal Plumbing:-75% work completed, Electrical Internal wall chasing & Box fitting:-85% completed, wire pulling :-50% completed, Ramp work :-30% completed, Tiling work :-40% completed, Internal Putty work :-85% completed, Balcony handrail fixing:-80% completed.

Progress as of January 2017

Block work:-98% work completed, Internal Plastering :- 80% work completed, External plastering :- 65% work completed, Internal Plumbing:-75% work completed, Electrical Internal wall chasing & Box fitting:-65% completed, wire pulling :-40% completed, Ramp work :-30% completed, Tiling work :-35% completed, Internal Putty work :-75% completed, Balcony handrail fixing:-80% completed.

Verna progress as of December 2016

Block work:-98% work completed, Internal Plastering :- 70% work completed, External plastering :- 50% work completed, Internal Plumbing:-60% work completed, Electrical Internal wall chasing & Box fitting:-65% completed, wire pulling :-25% completed, Ramp work :-30% completed, Tiling work :-20% completed, Internal Putty work :-50% completed, Balcony handrail fixing:-80% completed.

Verna as of November 2016

External brick work completed. Internal brick and plastering work 70% completed. External plastering 60% completed and plumbing work 90% completed.

Roof Floor Slab Completed as on -14-08-2016
11th floor slab completed as on-24-07-2016
10th Floor slab completed as on 24-06-2016
9Th Floor Completed as on-01-06-2016
8th Floor slab completed as on 07-05-2016
7th Floor Slab Completed as on -10-04-2016
6th Floor Slab Completed as on 20-03-2016-Verna
5th Floor Slab Completed As on -28-02-2016
4th Floor slab completed as on -05-02-2016.
3rd Floor Slab Completed as on 08-01-2016
Ground Floor Slab Completed as on 26-08-2015
Foundation work completed as on 06-07-2015