Tana



tana-single-page

TANA– A revolutionary approach for those customers whose aesthetics seek out the extra flavor to please their palette with living spaces. We understand the influence of the wide open information Highway.

Location : Ambalamuku, Trivandrum
Type of Units : 2BHK, 3BHK, 3BHK + Study & 4BHK
Building permit No : E10/BA/235/12
Airport authority of india NOC ID : THIR/SOUTH/B/103012/007

Online booking form

Actual images of TANA sample Apartment

Common amenities
  • CCTV
  • Bio-metric Entry for entrance lobby
  • Fitness centre
  • Wi-Fi
  • Video Door phone
  • Stretcher Lift
  • Roof top party area
  • Cable TV
  • Kid’s play area
  • Guest Suite
  • Association room
Resource Conservation
  • Rain water harvesting
  • Solar Energy for Yard & Common area Lighting

Nearby Convenience within 3 kms radius

Schools Christ Nagar, ISC Holy Angels, Nirmala Bhavan, Salvation Army
Colleges H H. The Maharaja’s Govt. College for women. Law Academy, Mar Ivanious, Mar Basellious, MG College
Hospitals Swanthwana, SUT, Cosmopolitan, Medical College, RCC.
Departmental Stores and Shoping Centres More For You, Azad Bread Factory, Nilgiris, Reliance Fresh
Entertainment Museum & Zoo, Tennis Club, Nishagandhi, Kalabhavan Theratre
Hotels & Restaurant Taj Vivantha, Windstor rajadhani, Sindoor Palace, Kalavara.
Progress as of September 2017

Block work – 100% completed, Internal Plastering –90 % work completed, External plastering – North-100%,West-92%, South.100% East-90% work completed, Internal Plumbing – 72% work completed, Electrical Internal wall chasing & Box fitting – 98% completed, wire pulling – 58% completed, Balcony handrail fixing – 76% Completed . Internal Putty Work –45% Completed, Tiling Work-20% Completed. Sump Tank work -100% Completed, Retaining Wall Works-100% Completed, Stair handrail-10% Completed.

Progress as of August 2017

Block work – 100% completed, Internal Plastering –89 % work completed, External plastering – North-100%,West-92%, South.100% East-90% work completed, Internal Plumbing – 70% work completed, Electrical Internal wall chasing & Box fitting – 98% completed, wire pulling – 55% completed, Balcony handrail fixing – 75% Completed . Internal Putty Work –45% Completed, Tiling Work-15% Completed. Sump Tank work -100% Completed, Retaining Wall Works-100% Completed. ​​

Progress as of July 2017

Block work – 100% completed, Internal Plastering – 87% work completed, External plastering – North-100%,West-87%, South.100% East-80% work completed, Internal Plumbing – 60% work completed, Electrical Internal wall chasing & Box fitting – 98% completed, wire pulling – 45% completed, Balcony handrail fixing – Sample Completed . Internal Putty Work –15% Completed, Tiling Work-10% Completed. Sump Tank work -40% Completed, Retaining Wall Works-100% Completed. ​

Progress as of June 2017

Block work – 100% completed, Internal Plastering – 86% work completed, External plastering – North-100%,West-85%, South.100% East-80% work completed, Internal Plumbing – 56% work completed, Electrical Internal wall chasing & Box fitting – 97% completed, wire pulling – 35% completed, Balcony handrail fixing – Sample Completed . Internal Putty Work –Started, Tiling Work-5% Completed. Sump Tank work -20% Completed, Retaining Wall Works-100% Completed.​

Progress as of  May 2017

Block work – 100% completed, Internal Plastering – 85% work completed, External plastering – North-100% ,West-80%, South.100% East-70% work completed, Internal Plumbing – 55% work completed, Electrical Internal wall chasing & Box fitting – 95% completed, wire pulling – 30% completed, Balcony handrail fixing – Sample Completed . Internal Putty Work –Started, Tiling Work-Just Started. Sump Tank work -Just Started, Retaining Wall Works-Completed.​

Progress as of  April 2017

Block work – 100% completed, Internal Plastering – 80% work completed, External plastering – North-100% ,West-60%, South.100% East-60% work completed, Internal Plumbing – 55% work completed,Electrical Internal wall chasing & Box fitting – 80% completed, wire pulling – 30% completed, Balcony handrail fixing – Sample Completed . Internal; Putty Work – Just Started

Progress as of March 2017

Block work:-100% work completed, Internal Plastering :- 80% work completed, External plastering :- 60% work completed, Internal Plumbing:-50% work completed, Electrical work:-60% completed

Progress as of February 2017

Block work:-100% work completed, Internal Plastering :- 65% work completed,
External plastering :- 55% work completed, Internal Plumbing:-40% work completed, Electrical work:-45% completed

Progress as of January 2017

Block work:-99% work completed, Internal Plastering :- 55% work completed,
External plastering :- 30% work completed, Internal Plumbing:-15% work completed, Electrical work:-40% completed

Tana progress as on December 2016

Block work:-90% work completed, Internal Plastering :- 40% work completed,
External plastering :- 10% work completed, External Plumbing:-5% work completed, Electrical work:-30% completed,

Tana November 2016 progress

External brick work has been completed. Internal brick and plastering work 50% has been completed. Plumbing and flooring works are under progress.

Roof Floor Slab Completed as on-12-07-2016
10th floor slab completed as on-25-05-2016
9th floor slab completed as on-03-02-2016
8th floor slab completed as on-09-01-2016
TANA fifth floor stab has been completed on 13-08-2015.
Fourth floor slab completed as On -23-07-2015
Third floor slab completed as On -30-06-2015
Second floor slab completed as On -20-05-2015
First floor slab completed as on 18-04-2015

Download E-broucher

DOWNLOAD-E-BROUCHER