TANA– A revolutionary approach for those customers whose aesthetics seek out the extra flavor to please their palette with living spaces. We understand the influence of the wide open information Highway.
Location : Ambalamuku, Trivandrum
Type of Units : 2BHK, 3BHK, 3BHK + Study & 4BHK
Building permit No : E10/BA/235/12
Airport authority of india NOC ID : THIR/SOUTH/B/103012/007
Actual images of TANA sample Apartment
Common amenities
- CCTV
- Bio-metric Entry for entrance lobby
- Fitness centre
- Wi-Fi
- Video Door phone
- Stretcher Lift
- Roof top party area
- Cable TV
- Kid’s play area
- Guest Suite
- Association room
Resource Conservation
- Rain water harvesting
- Solar Energy for Yard & Common area Lighting
Nearby Convenience within 3 kms radius |
|||||
Schools | Christ Nagar, ISC Holy Angels, Nirmala Bhavan, Salvation Army | ||||
Colleges | H H. The Maharaja’s Govt. College for women. Law Academy, Mar Ivanious, Mar Basellious, MG College | ||||
Hospitals | Swanthwana, SUT, Cosmopolitan, Medical College, RCC. | ||||
Departmental Stores and Shoping Centres | More For You, Azad Bread Factory, Nilgiris, Reliance Fresh | ||||
Entertainment | Museum & Zoo, Tennis Club, Nishagandhi, Kalabhavan Theratre | ||||
Hotels & Restaurant | Taj Vivantha, Windstor rajadhani, Sindoor Palace, Kalavara. |
[Best_Wordpress_Gallery id=”7″ gal_title=”Tana floor plan”]
Progress as of October 2018
Block work – 100% completed, Internal Plastering –100% work completed, External plastering – North-100%, West-100%, South.100% East-100% work completed, Internal Plumbing – 100% work completed, Electrical Internal wall chasing & Box fitting – 100% completed, wire pulling – 90% completed, Balcony handrail fixing – 100% Completed. Internal Putty Work –100% Completed, Tiling Work-95% Completed. Lobby tiling-100% Completed, Sump Tank work -100% Completed, Retaining Wall Works-100% Completed, Stair handrail-100% Completed. External Putty work-100% Completed. First Coat External Paint-100% Completed, Ramp Work-90%Completed, Fire Protection Work-100% Completed, Main Door structure fixing-100% completed, Internal Doors and Windows –60%, Staircase Tiling-100% completed, Granite Work-100%, Compound Wall-95%, Lift Work-97% Completed. Aluminium Sliding doors and windows-70% Completed.
[Best_Wordpress_Gallery id=”161″ gal_title=”Tana 2018 October”]
Progress as of July 2018
Block work – 100% completed, Internal Plastering –100% work completed, External plastering – North-100%, West-98%, South.100% East-100% work completed, Internal Plumbing – 100% work completed, Electrical Internal wall chasing & Box fitting – 100% completed, wire pulling – 90% completed, Balcony handrail fixing – 100% Completed. Internal Putty Work –100% Completed, Tiling Work-86%
Completed. Lobby tiling-98% Completed, Sump Tank work -100% Completed, Retaining Wall Works-100% Completed, Stair handrail-100% Completed. External Putty work-100% Completed. First Coat External Paint-100% Completed, Ramp Work-75%Completed, Fire Protection Work-95% Completed, Main Door structure fixing-100% completed, Inernal Doors and Windows – 50%, Staircase Tiling-100% completed, Granite Work-80%, Compound Wall-80%, Lift Work-95% Completed. Aluminium Sliding doors and windows-50% Completed.
[Best_Wordpress_Gallery id=”156″ gal_title=”Tana july 2018″]
Progress as of May 2018
Block work – 100% completed, Internal Plastering –99% work completed, External plastering – North-100%, West-98%, South.100% East-100% work completed, Internal Plumbing – 95% work completed, Electrical Internal wall chasing & Box fitting – 100% completed, wire pulling – 85% completed, Balcony handrail fixing – 95% Completed. Internal Putty Work –100% Completed, Tiling Work-85% Completed. Lobby tiling-90% Completed, Sump Tank work -100% Completed, Retaining Wall Works-100% Completed, Stair handrail-100% Completed. External Putty work-100% Completed. First Coat External Paint-100% Completed, Ramp Work-70%Completed, Fire Protection Work-80% Completed, Main Door structure fixing-100% completed, Inernal Doors and Windows – 50%, Staircase Tiling-98% completed, Granite Work-70%, Compound Wall-60%, Lift Work-40% Completed.
[Best_Wordpress_Gallery id=”152″ gal_title=”2018-May-Tana”]
Progress as of January 2018
Block work – 100% completed, Internal Plastering –98% work completed, External plastering – North-100%, West-98%, South.100% East-100% work completed, Internal Plumbing – 90% work completed, Electrical Internal wall chasing & Box fitting – 100% completed, wire pulling – 75% completed, Balcony handrail fixing – 79% Completed. Internal Putty Work –80% Completed, Tiling Work-70% Completed. Sump Tank work -100% Completed, Retaining Wall Works-100% Completed, Stair handrail-100% Completed. External Putty work-100% Completed.
[Best_Wordpress_Gallery id=”148″ gal_title=”Tana January 2018″]
Progress as of December 2017
Block work – 100% completed, Internal Plastering –94% work completed, External plastering – North-100%, West-95%, South.100% East-93% work completed, Internal Plumbing – 82% work completed, Electrical Internal wall chasing & Box fitting – 98% completed, wire pulling – 63% completed, Balcony handrail fixing – 79% Completed. Internal Putty Work –65% Completed, Tiling Work-53% Completed. Sump Tank work -100% Completed, Retaining Wall Works-100% Completed, Stair handrail-60% Completed. External Putty work-55% Completed.
[Best_Wordpress_Gallery id=”78″ gal_title=”December 2017″]
Progress as of November 2017
Block work – 100% completed, Internal Plastering –92% work completed, External plastering – North-100%, West-94%, South.100% East-92% work completed, Internal Plumbing – 80% work completed, Electrical Internal wall chasing & Box fitting – 98% completed, wire pulling – 60% completed, Balcony handrail fixing – 77% Completed. Internal Putty Work –60% Completed, Tiling Work-50% Completed. Sump Tank work -100% Completed, Retaining Wall Works-100% Completed, Stair handrail-60% Completed. External Putty work-50% Completed
[Best_Wordpress_Gallery id=”77″ gal_title=”Tana November 2017″]
Progress as of October 2017
Block work – 100% completed, Internal Plastering –92% work completed, External plastering – North-100%,West-93%, South.100% East-90% work completed, Internal Plumbing – 79% work completed, Electrical Internal wall chasing & Box fitting – 98% completed, wire pulling – 60% completed, Balcony handrail fixing – 76% Completed . Internal Putty Work –50% Completed, Tiling Work-40% Completed. Sump Tank work -100% Completed, Retaining Wall Works-100% Completed, Stair handrail-50% Completed. External Putty work-10% Completed.
[Best_Wordpress_Gallery id=”73″ gal_title=”Tana Oct 2017″]
Progress as of September 2017
Block work – 100% completed, Internal Plastering –90 % work completed, External plastering – North-100%,West-92%, South.100% East-90% work completed, Internal Plumbing – 72% work completed, Electrical Internal wall chasing & Box fitting – 98% completed, wire pulling – 58% completed, Balcony handrail fixing – 76% Completed . Internal Putty Work –45% Completed, Tiling Work-20% Completed. Sump Tank work -100% Completed, Retaining Wall Works-100% Completed, Stair handrail-10% Completed.
[Best_Wordpress_Gallery id=”72″ gal_title=”Tana Sept 2017″]
Progress as of August 2017
Block work – 100% completed, Internal Plastering –89 % work completed, External plastering – North-100%,West-92%, South.100% East-90% work completed, Internal Plumbing – 70% work completed, Electrical Internal wall chasing & Box fitting – 98% completed, wire pulling – 55% completed, Balcony handrail fixing – 75% Completed . Internal Putty Work –45% Completed, Tiling Work-15% Completed. Sump Tank work -100% Completed, Retaining Wall Works-100% Completed.
[Best_Wordpress_Gallery id=”67″ gal_title=”August_Tana_2017″]
Progress as of July 2017
Block work – 100% completed, Internal Plastering – 87% work completed, External plastering – North-100%,West-87%, South.100% East-80% work completed, Internal Plumbing – 60% work completed, Electrical Internal wall chasing & Box fitting – 98% completed, wire pulling – 45% completed, Balcony handrail fixing – Sample Completed . Internal Putty Work –15% Completed, Tiling Work-10% Completed. Sump Tank work -40% Completed, Retaining Wall Works-100% Completed.
[Best_Wordpress_Gallery id=”59″ gal_title=”2017-July_Tana”]
Progress as of June 2017
Block work – 100% completed, Internal Plastering – 86% work completed, External plastering – North-100%,West-85%, South.100% East-80% work completed, Internal Plumbing – 56% work completed, Electrical Internal wall chasing & Box fitting – 97% completed, wire pulling – 35% completed, Balcony handrail fixing – Sample Completed . Internal Putty Work –Started, Tiling Work-5% Completed. Sump Tank work -20% Completed, Retaining Wall Works-100% Completed.
[Best_Wordpress_Gallery id=”56″ gal_title=”June 2017-Tana”]
Progress as of May 2017
Block work – 100% completed, Internal Plastering – 85% work completed, External plastering – North-100% ,West-80%, South.100% East-70% work completed, Internal Plumbing – 55% work completed, Electrical Internal wall chasing & Box fitting – 95% completed, wire pulling – 30% completed, Balcony handrail fixing – Sample Completed . Internal Putty Work –Started, Tiling Work-Just Started. Sump Tank work -Just Started, Retaining Wall Works-Completed.
[Best_Wordpress_Gallery id=”45″ gal_title=”Tana 2017 -May”]
Progress as of April 2017
Block work – 100% completed, Internal Plastering – 80% work completed, External plastering – North-100% ,West-60%, South.100% East-60% work completed, Internal Plumbing – 55% work completed,Electrical Internal wall chasing & Box fitting – 80% completed, wire pulling – 30% completed, Balcony handrail fixing – Sample Completed . Internal; Putty Work – Just Started
[Best_Wordpress_Gallery id=”40″ gal_title=”Tana-April 2017″]
Progress as of March 2017
Block work:-100% work completed, Internal Plastering :- 80% work completed, External plastering :- 60% work completed, Internal Plumbing:-50% work completed, Electrical work:-60% completed
[Best_Wordpress_Gallery id=”38″ gal_title=”Tana-March17″]
Progress as of February 2017
Block work:-100% work completed, Internal Plastering :- 65% work completed,
External plastering :- 55% work completed, Internal Plumbing:-40% work completed, Electrical work:-45% completed
[Best_Wordpress_Gallery id=”36″ gal_title=”TANA-FEB-17″]
Progress as of January 2017
Block work:-99% work completed, Internal Plastering :- 55% work completed,
External plastering :- 30% work completed, Internal Plumbing:-15% work completed, Electrical work:-40% completed
[Best_Wordpress_Gallery id=”34″ gal_title=”Tana 2017″]
Tana progress as on December 2016
Block work:-90% work completed, Internal Plastering :- 40% work completed,
External plastering :- 10% work completed, External Plumbing:-5% work completed, Electrical work:-30% completed,
[Best_Wordpress_Gallery id=”32″ gal_title=”December-Tana-2016″]
Tana November 2016 progress
External brick work has been completed. Internal brick and plastering work 50% has been completed. Plumbing and flooring works are under progress.
[Best_Wordpress_Gallery id=”29″ gal_title=”Tana November”]
Roof Floor Slab Completed as on-12-07-2016
[Best_Wordpress_Gallery id=”26″ gal_title=”Tana roof floor”]
10th floor slab completed as on-25-05-2016
[Best_Wordpress_Gallery id=”23″ gal_title=”Tana 10th Floor”]
9th floor slab completed as on-03-02-2016
[Best_Wordpress_Gallery id=”17″ gal_title=”Tana 9th Floor”]
8th floor slab completed as on-09-01-2016
[Best_Wordpress_Gallery id=”15″ gal_title=”Tana 8th Floor”]
TANA fifth floor stab has been completed on 13-08-2015.
[Best_Wordpress_Gallery id=”13″ gal_title=”Tana 5th Floor”]
Fourth floor slab completed as On -23-07-2015
[Best_Wordpress_Gallery id=”12″ gal_title=”Tana 4th floor slap”]
Third floor slab completed as On -30-06-2015
[Best_Wordpress_Gallery id=”2″ gal_title=”Tana-Third floor slab completed”]
Second floor slab completed as On -20-05-2015
[Best_Wordpress_Gallery id=”4″ gal_title=”tana 2nd floor”]
First floor slab completed as on 18-04-2015
[Best_Wordpress_Gallery id=”3″ gal_title=”Tana 1st floor”]
[Best_Wordpress_Gallery id=”9″ gal_title=”Tana route map”]